In agreement with Cornwall Councillor Mike McLening, Cornwall Council has committed £400k for a programme of works within St Stephen in Brannel.  The aim of this is to address speed concerns and improve road safety.  Cormac are progressing this project, with public consultation undertaken recently in December/January.  A breakdown of the works, with associated timescales for construction is as follows:

Year 1

Construction start 22nd April 2021

Year 2

Construction by March 2022

Year 3

Construction by March 2023

Terras-St Stephen gateway build-outs enlargement High Street footway Park Gwyn crossing point
Creakavose junction modification/crossing point and footway extension Gwindra Road footway widening at ‘Peugeot Hawkins Motors’
Crossing point across Terras Road from Creakavose
Park Gwyn school crossing patrol advisory 20mph limit signage
Churchtown Road “No left turn” signage
Churchtown Road junction modification/crossing point
Churchtown Road and Churchtown Meadows 20mph Zone and traffic calming
Gwindra Road bus stop waiting area surfacing
Gwindra Road gateway speed limit terminal relocation and traffic calming build-outs
Long Lane-Tremarne Camp Site gateway signage moving
Long Lane footway adjacent to ‘Trelay’
Long Lane footway from ‘Trelay’ to B3279 junction at High Street

Information signs will be erected on site, in advance of each phase of construction being undertaken.