The Parish Council has received the following e-mail. Any queries should be directed to Suez.

I am writing to inform you that on Monday 03 August 2020, Western Power will be carrying out essential maintenance on the substation based at the Cornwall energy recovery centre (CERC). The work will take approximately four days to complete and during this time supply and export to the national grid will be suspended.

Whilst the maintenance work is taking place, the CERC will run on island mode supplying internal power only. We are not anticipating any disruptions to the operations and will continue to process Cornwall’s household waste as usual.