The Parish Council has received the following e-mail. Any queries should be directed to Suez.

We are writing to update you on this phase of the CERC roof repair works.  The works have recommenced this week after delays during December due to adverse weather conditions and will continue throughout January and February.

We have been working with our contractor VINCI to expedite their works and as a result they have requested further weekend working early in the New Year. This weekend working will be limited to the hours of 8:00am and 4:00pm. VINCI returned to site on 4th January 2021 and plan to work over the following weekends:

  • 09 and 10 January 2021
  • 23 and 24 January 2021
  • 06 and 07 February 2021
  • 20 and 21 February2021

This additional weekend working will enable the first stage of repairs to be completed as swiftly as possible.

Due to the challenges associated with the poor weather at this time of year, the contractors may need to work flexibly and adjust plans if required.  We will provide further updates if this becomes necessary.